More than ten thousand households are ready for electrical energy! 4000 connections of service line and 7000 connections of job work are pending


Jaipur: The orders to offer electrical energy connections of service traces inside 24 hours within the state are proving to be futile. In Jaipur Discom alone, greater than ten thousand households are ready for electrical energy connection for a very long time. Out of those, there are greater than 4 thousand households the place the connection needs to be given by drawing service line from the pole, however because of the arbitrariness of the engineers, the shoppers are disadvantaged of electrical energy.

The intention of the Rajasthan authorities is that electrical energy shoppers ought to get the most effective amenities. Keeping this intention in thoughts, the Rajasthan Discom administration applied the brand new system from February 1 and instructed that wherever connections are to be constructed from the service line, electrical energy provide needs to be began inside 24 hours of the patron’s software. After the order issued by the then CMD Bhanuprakash Eturu, reminders have been additionally issued twice, however until now the engineers within the area are working within the outdated means. Its actuality was seen within the first evaluate assembly of CMD Aarti Dogra, who lately took over the accountability of Discom. The information of 20 circles of Discom was offered within the assembly, by which 11161 electrical energy connections have been proven pending. However, after reviewing these figures, the CMD has instructed all the sphere engineers to finish the pendency of home connections as quickly as doable.

Jaipur Discom: Official information of excellent connections
Bharatpur Zone ::::::: 5309 connections pending
Out of this, 2446 connections are of service line, whereas 2863 connections are for job work.
,
Jaipur Zone :::::::: 4299 connections pending
Out of this, 882 connections are of service line, whereas 3417 connections are for job work.
,
Kota Zone :::::::: 1553 Connections Pending
Out of this, 752 connections are of service line, whereas 801 connections are for job work.

Amazing working type of the capital’s electrical energy engineers…!
News associated to the reality of Jaipur Discom’s authorities records-field
As per the data, solely 18 purposes for electrical energy connection are pending in Jaipur metropolis
In Jaipur South Circle, not even a single client’s connection is pending
In Jaipur North Circle, six service line connections and 12 job work connections are pending
Whereas the reality is that after making use of, a whole bunch of shoppers are making rounds
In such a state of affairs, the query is whether or not CMD Aarti Dogra will evaluate these authorities figures?
If engineers are issuing on-demand connections, they are going to be inspired
And if there’s any error within the information, such engineers will probably be recognized and “punished”

Regarding this, Minister of State for Energy Hiralal Nagar says that it’s our precedence to situation all pending electrical energy connections earlier than Diwali. Discom CMD has been instructed to situation pending connections as quickly as doable. Where there’s a drawback of fabric in making connections, separate provide has been requested for there. Instructions for monitoring have additionally been given to area officers from the headquarters degree.



Source link