UDH Minister Jhabar Singh Kharra units deadline for JDA’s Neendar scheme positioned on Sikar Road, see this particular report


Jaipur: There is hope for a everlasting resolution to the Neendad scheme which can give Rs 1000 crore to the JDA treasury, pending for the final 14 years. The Urban Development Minister has set a deadline of October to unravel the issue. JDA had proposed an enormous housing scheme 14 years in the past in village Neendar on the principle Sikar Road of Jaipur. Their land was additionally taken away from many farmers within the title of the scheme. Neither the scheme could possibly be absolutely carried out nor the farmers have been in a position to get compensation until now regardless of giving their land. This scheme is so large and the present market right here. Talking concerning the value, JDA can get income of about Rs 1000 crore from this scheme alone. Four years in the past, a bit of farmers had agitated demanding larger compensation. After that this matter went into chilly storage. But seeing the significance of this scheme, the state authorities has determined to implement it. Let us first provide you with details about the scheme

Scheme Information:
-This Neendar residential scheme is proposed in 327 hectares.
-The first notification for the acquisition of about 286 hectares of land was issued on January 4, 2010.
-The remaining 41.45 hectares of land is JVP’s personal land.
-Land acquisition award issued on 31 May 2013
-Cash compensation of 41.27 hectares of land has been deposited within the civil courtroom.
-The High Court has rejected the petitions filed by the farmers in opposition to the acquisition.
-The Supreme Court has additionally accepted the method of acquisition as right in its order of 4 September 2018.
-Around 600 account holders have devoted 122 hectares of their land in favor of JDA.

About 600 account holders affected by the scheme have given their very own land to JDA. Many of those account holders have been ready for compensation for giving their land for the final 8 to 10 years. A memorandum was additionally given to Chief Minister Bhajan Lal Sharma, Deputy Chief Minister Diya Kumari and Urban Development Minister Jhabar Singh Kharra on behalf of Neendar Reservation Patra Dhari Kisan Sangharsh Samiti demanding quick compensation.

Sleeper Scheme, there shall be an answer!:
-JDA has issued reservation letters to about 450 account holders who’ve given land.
-Reservation letter has been given to those account holders to offer 20% residential and 5% business land.
-On 27 November 2017, JDA had allotted plots to about 90 account holders.
-Farmers demand that we have now given our land
-We don’t have any land left to stay on
-In such a scenario, JDA had allotted plots via lottery to construct homes.
-But compensation for the complete 25% developed plot was not given
-There are about 150 account holders who had surrendered their land to JDA by the 12 months 2020.
-But JDA has not issued them reservation letters even after 4 years.
-In this manner, about 600 account holders or farmers have given their land for the scheme.
-But JDA has not but given them full compensation for the developed plot.
-JDA began work right here on 1 January 2020
-But a bit of farmers began a motion demanding extra compensation.
-Later, a gathering was additionally held on the stage of JDA and state authorities concerning the calls for of those farmers.
-After this the matter was shelved

This Neendar residential scheme proposed on the land of alternative in entrance of Harmada on Sikar Road can fill the coffers of JDA. This is the rationale why the state authorities is critical about this scheme. Urban Development Minister Jhabar Singh Kharra says that this plan shall be given concrete form quickly. Let us let you know how this scheme will show to be Kuber’s treasure for JDA and what deadline has been set by Urban Development Minister Jhabar Singh Kharra on this matter.

What deadline has been mounted on this matter:
-This scheme is just one and a half to 2 kilometers from culvert quantity 14.
-The land of the scheme is adjoining to Sikar Road.
-Here residential and business market costs vary from Rs 40 thousand to Rs 1 lakh per sq. yard.
-40 % of this whole plan is proposed for amenity areas and roads.
-25 % land is to be given to farmers as compensation
-In this manner JDA shall be left with 35 % land.
-If the market value right here is taken into account to be a mean of ₹ 60 thousand per sq. yard
-So JDA can get income of round Rs 1000 crore
-UDH Minister Jhabar Singh Kharra advised First India
-He has given directions to JDA Commissioner Anandi to resolve the problems associated to this scheme.
-The downside of farmers/accountants who willingly give up their land for the scheme shall be solved.
-After this, after listening to the aspect of different farmers/accountants, motion shall be taken on their calls for as per guidelines.

UDH Minister Jhabar Singh Kharra stated that critical efforts concerning the scheme shall be began by October subsequent month.